How do I compare shopfront quotes?

Compare quotes line by line against the same drawing, checking glass make-up, frame finish, door gear, removal, making good, access, licences and exclusions. The lowest total often leaves something out, and a higher one may be covering work the others will charge for later. Ask each contractor to price the same specification, and check who the contract is actually with.

Written by the Shopfront Specialists team. Checked November 2026.

Scale elevation drawing of a shopfront with material samples laid out on a design table

How do I compare shopfront quotes fairly?

Give every contractor the same brief, the same drawing and the same list of exclusions, then compare line by line. Totals mean very little until you know that each one prices the same job. If each contractor has designed their own frontage from a phone call, you are comparing three different shopfronts.

A short written brief solves most of this. State the opening size, the materials you have in mind, the door type, the sign, whether you want a shutter, and any trading limits. Ask each firm the same questions in writing, so that the answers can be compared. Put them into a simple spreadsheet with one row per item and one column per contractor, and blank cells will soon show who has left what out.

LineA clear quote saysWarning sign
GlassMake-up of each pane"Safety glass" with no detail
FrameDepth, face width, colour reference"Aluminium frame" alone
DoorCloser, lock, handle, threshold"Door included"
RemovalOld front out and disposed ofNot mentioned
Making goodWhat is finished, and to what levelNot mentioned
AccessScaffold, licences, loading"Subject to site"
HoursNormal or out-of-hours statedNot mentioned

Why do shopfront quotes vary so much?

Quotes vary mainly because they are not pricing the same work. One may allow for 6.4mm laminated glass where another allows for 11.5mm, one for a standard powder coat and another for a special colour, one for a day shift and another for three nights. All of them can honestly be called a new aluminium shopfront.

Survey quality matters as well. A figure produced from a photograph has to include a guess, and the guess might be too low, in which case you meet it later as an extra. Where a quote is built on a measure-up, the awkward wall has already been found, so it can look high until the other firm's extras arrive.

Check how VAT is shown, too. Published prices and quotes across the trade mix net and gross figures, and a gap between two numbers may be nothing more than that. Ours are shown before VAT.

What do the glass, frame and door lines really tell me?

They tell you what you will actually live with for the next fifteen years. A glass line should give thickness and type for each pane, so that you can tell toughened from laminated and see any security rating. If it just says toughened, ask what happens to the shop after a brick goes through it.

A frame line should give section depth, face width and finish. Ask to see a sample corner: a mitred, sealed joint with a tidy gasket tells you more than any brochure. Look for a reference to the coating, such as a colour number and whether it is powder coat or anodised.

Door lines hide the most. A commercial door is its closer, floor spring, lock and handle, and those parts decide how it feels after a year of daily use. Ask how many of those parts are named, and who services them. The difference between a light-duty closer and a proper commercial one barely shows on a quote, and it shows every day after that.

What is usually left out of a low quote?

Low quotes usually leave out the work around the frontage, not the frontage itself. A line that doesn't appear hasn't been priced, and it may return as an extra once the job is under way. Check each of the items below and ask where it sits.

Making good causes more arguments than any other line. Taking out an old frame leaves torn plaster inside, cut tiles at the threshold and a scar along the pavement edge, and someone has to finish those. Agree what finished means before work starts, ideally with a photograph of a similar detail, because a fitter's idea of tidy may differ from yours.

  • Removing and disposing of the old shopfront
  • Temporary boarding and security overnight
  • Making good to stallriser, fascia, pavement edge and ceiling
  • Steelwork or repairs to the structure behind
  • Electrician's work for the sign, door and shutter
  • Scaffold, hoarding and highway licences
  • Drawings, consent applications and council fees
  • Out-of-hours working

How do I check the contractor behind the quote?

Check who you are contracting with, and whether the documents back up what the website says. The quote should name a legal entity, ideally with a company number, because a trading name by itself tells you little. Ask for the insurance certificate, and read the cover and the expiry date.

If a firm displays an accreditation, check it on the issuing body's own register. Ask to see product certificates for what is actually being fitted. A contractor should explain clearly who will be on your site and who answers the phone when something is wrong. For us, that means S&K Glazing Limited, company 14088194, trading as Shopfront Specialists, with vetted teams working under it and one named contact for the job.

Read the guarantee too. A headline number means little until you have seen the written terms, including what is covered, what isn't and who stands behind it. Ours is a 10-year workmanship guarantee, with terms set out in the quotation.

When is the lowest quote the right one?

The lowest quote is the right one when the specification, scope and terms really do match the others, and you are comfortable with the firm behind it. For a simple replacement on a plain unit, a smaller contractor with lower overheads may well offer fair value, and there is no shame in taking it.

We aren't the lowest-priced option and don't try to be. Shopfront Specialists is a measured, drawn and properly specified service, which suits owners who care about how a frontage looks in five years. If your job needs something simpler, a good comparison will tell you that, and it should.

Common questions

How many quotes should I get?

Three is a sensible number for most frontages. Fewer gives you little to compare, and many more just dilutes the time each contractor spends on your job.

Is a guide price the same as a quote?

No, a guide price is a budget band, and a quotation is a written price for a specified job. Ours are itemised, follow a measured survey and stay valid for 90 days.

What does provisional sum mean on a quote?

It is an allowance for work that can't be fully priced yet, such as repairs behind a fascia. Check how the final cost will be agreed, because the sum itself isn't a fixed price.

Should I always pay a deposit?

Many contractors ask for one, because glass and frames are made to order for your job. Check what it covers and when any stage payments fall due, and have that written into the contract.