A shopfront specification should set out performance, glass make-up by pane, frame type and finish, door and ironmongery function, tolerances, interfaces and who holds each consent. Name the standard each element is designed to meet, and ask for the certificate with the product where that applies. Keep the wording manufacturer-neutral unless the client has chosen a system, and state which nation's regulations govern.

Written by the Shopfront Specialists team. Checked November 2026.

Aluminium curtain walling with slim mullions across a two-storey commercial facade at dusk

What should a shopfront specification include?

It should describe what the frontage has to do, what it looks like and who designs what. A clear specification separates the architect's visual intent from the contractor's design portion, since sections, fixings and glass thickness often depend on a system chosen later.

State the sightline you want and the depth you can allow, and let the performance requirements do the rest. A dimension such as a maximum 50mm face tells a tenderer far more than an adjective, and a marked-up detail says more than either. If the drawings and the written clauses could ever disagree, say which of them takes priority.

  • Scope, and what is excluded, including electrical and alarm work
  • Frame type, face width, depth and finish reference
  • Pane schedule with make-up, class and edge finish
  • Door, ironmongery and hold-open schedule by function
  • Tolerances, setting-out datum and fixing background
  • Interfaces with fascia, sign, shutter, ceiling and threshold
  • Consents, who holds them and any conditions to discharge
  • Samples, mock-ups and approvals before fabrication

Which standards should a shopfront specification cite?

Cite the product standard for each element and ask the tenderer to declare what the product is tested to. Most shopfronts sit under BS EN 14351-1 for screens and external pedestrian doorsets, with BS EN 13830 taking over where the elevation is true curtain walling, and the CWCT standard for systemised building envelopes is the usual industry reference there.

Several of these are under review at BSI, including BS EN 13830, BS EN 14351-1, BS EN 13241, BS EN 356, BS EN 1627 and PAS 24, while a revision of BS 7036-0 has been proposed. Check the current edition when you issue the tender. Specify coatings by reference to the Qualicoat or Qualanod label, and request evidence from the applicator.

ElementReference
Screens and doorsetsBS EN 14351-1:2006+A2:2016
Curtain wallingBS EN 13830:2015+A1:2020
Glass impact classBS EN 12600:2002
Human impactBS 6262-4:2018
Security glazingBS EN 356:2000
Burglar resistanceBS EN 1627:2021, PAS 24:2022, LPS 1175 Issue 8.2
Powered doorsBS EN 16005:2023, BS 7036-0:2014
ClosersBS EN 1154
Exit devicesBS EN 1125:2008, BS EN 179:2008
ShuttersBS EN 13241:2003+A2:2016

How should glass be specified on a shopfront?

Specify glass pane by pane in a schedule, giving make-up, class, edge finish, manifestation and approximate weight. A general note saying safety glass where required leaves too much to chance, and it gives the tenderer room to price something else.

Write the safe-breakage class to suit the nation: BS EN 12600 for England and Northern Ireland, BS 6206 in Wales under Approved Document N, and BS 6262-4 in Scotland, then confirm with the checking body. Call for low-iron glass where edges show, state whether toughened panes are heat-soaked, and set the roller-wave direction for matched reflections across a run.

Weight is a design input. Show it on the schedule so that the structural engineer can check the head, the cills and any old beam, because Historic England's warning about heavier glass applies to more than listed fronts.

How should the interfaces be detailed?

Detail the head, cill and jamb before tender, because most shopfront failures happen at junctions. At the head, allow for deflection of the structure above and show how the frame or channel takes it. Lower down, show the damp-proof course, the threshold upstand and where water goes, and give a maximum upstand of 15mm at accessible doors.

Set out from a stated datum. Street levels fall, old floors roll, and a frontage drawn from a single spot height can be 40mm out at the far end. Ask for a site check after strip-out and before fabrication, and write that hold point into the programme.

Coordinate the void above the glass. Fascia depth, shutter box, sign cable, blind box and ceiling all want the same 300mm, and they rarely agree unless somebody draws the section at 1:5 before tender.

Which building regulations apply to a shopfront?

That depends on the nation, so name it in the specification. England uses Approved Documents K, M Volume 2, B Volume 2, L Volume 2 and A if structure changes. Wales keeps Part N, with its own Approved Document M and Approved Document B. Scotland uses the Technical Handbook, with the April 2026 edition applying to warrants from 6 April 2026. Northern Ireland uses Technical Booklets E, H, R, V and F2.

Assume notification. England and Wales have no like-for-like exemption, and registered installers can self-certify replacement windows and doors in non-dwellings, but not structural glass, curtain walling or revolving doors. External doors with 50% or less glazing are exempt under Schedule 4. In Scotland a replacement door or window with frame needs no warrant, though the standards still apply, while altering a wall or structure probably does need one, and in Northern Ireland shops are likely to go by full plans.

For energy, England's Table 4.1 gives 1.6 W/m²K for pedestrian doors and 3.0 for high-usage entrance doors, with no maximum for display windows. The 2026 Part L editions take effect on 24 March 2027 in England and 4 March 2027 in Wales.

What should the specification say about duties and handover?

It should identify the dutyholders and list what the contractor hands over. On a multi-contractor job, CDM 2015 calls for a principal designer and principal contractor in Great Britain, with CDM (NI) 2016 applying in Northern Ireland. England also expects clients to appoint competent people, Wales has Part 2A completion notices, and English buildings of 18m or 7 storeys with two homes need Building Safety Regulator approval unless the work is exempt or under a competent person scheme.

Ask for as-built drawings, the pane schedule, coating references, the powered door risk assessment and the maintenance instructions. Those papers are what an owner reaches for when a pane breaks in eight years' time.

Common questions

Should I name a specific aluminium system?

Only if the client has a reason. A performance specification with a stated sightline keeps the tender open, and a sample can settle the look.

Who carries design responsibility for the frame and glass?

The specification should say so explicitly, element by element. We prepare scale drawings for approval, so any contractor-designed portion is clear before anything is made.

What is the slimmest aluminium sightline I can draw?

Around 50mm is a realistic starting point for a commercial frame, and slimmer is possible on fixed lights. Height, wind exposure and the door gear decide what actually works.

Can you price from my drawings without a survey?

We can give a budget figure from drawings, but a firm quotation comes from a measured survey. The survey is free for new shopfronts, and it also tests the drawing against the opening.